Burn Up Chart Tool


This is an example burn-up chart that can be created either manually, or with AI tools. Check out the blog for step by step instructions and the overview video for more insights!

A burn-up chart tracks two things over time: the total scope of your project as you understand it today, and how much of that scope is actually done. Plotted together, the two lines tell you at a glance whether you’re on pace, whether scope is growing faster than the team can absorb it, and where risk is building — early enough to do something about it.

It runs on four data points you likely already have: the expected outcome, a sized backlog, story status, and dates. Everything else is built from there.


Burn Up — Project Progress

261 story points across 90 backlog items · target completion Friday, December 4, 2026

Total scope
261 pts
Completed to date
62 pts (24%)
Required pace
18.6 pts/wk
Actual pace so far
12.4 pts/wk
Cumulative points complete vs. required pace

Weekly points reflect the “week ending” date on stories marked done. Solid blue = actual completed work. Dashed orange = pace required to finish all scope by the Dec 4 deadline. Dashed gray = total scope. Data current through the week ending Oct 2, 2026.

Progress by workstream

Bar width shows each workstream’s share of total scope (261 pts); the filled portion shows points completed within that workstream.


Check out the step-by-step blog on creating a simple burn-up.